After investing around €21.6 million in the construction of the Elbasan incinerator and while it is planned that by 2027 urban waste will be transported to Shkodra, since the incinerator is practically not functioning, the government has included in the list of investments of national importance a new project worth 16.77 million euros for waste management infrastructure in Elbasan.
Besides being out of service, the Elbasan incinerator has been at the center of SPAK investigations with accusations of corruption and abuse of office for the officials involved. Recently, the administrator of the managing company ECI-ELB is also being investigated for taking bribes.
The new investment, recently proposed by the Ministry of Environment, has been immediately classified as mature, with an institutional priority level of A, and is ranked in the waste and landfill management sub-sector.
The project’s inclusion on the list of priority investments comes at a time when Elbasan, despite investments made over the years, still does not have a sustainable solution for managing urban waste.
After €21.6 million for the incinerator, waste heads to Shkodra
According to the National Sectoral Plan for Solid Waste Management, published by the Ministry of Infrastructure and Energy, the investment cost for the incineration plant in Elbasan was approximately €21.6 million.
The plant, built in Bradashesh under a concession contract, was intended to provide a long-term solution for the management of urban waste, while also enabling energy production from it.
However, following ongoing problems with the incinerator’s operation and its transfer to the public company ECO-ELB, the draft 2027 budget documents outline a different scheme for waste management.
As previously reported by Ekofin.al, eight municipalities—Elbasan, Librazhd, Rrogozhinë, Peqin, Cërrik, Belsh, Prrenjas, and Gramsh—are expected to receive funding for transporting urban waste to the waste management facility in Shkodër.
For this purpose, transfers from the state budget are planned, while the municipalities will also have to contribute from their own revenues.
Thus, in addition to the costs of investing in and managing the existing infrastructure in Elbasan, the public finances will also be burdened with the bill for transporting waste to another part of the country.
At the same time, the government is already planning another investment of nearly 17 million euros in Elbasan, without clarifying whether transporting waste to Shkodra will be a temporary solution until the new project is realized.
The previous cost of building the incinerator and the indicative value of the new project together amount to about 38.37 million euros, not including administrative, maintenance, and waste transportation expenses.
Elbasan also faces 1.5 million tons of industrial waste
The waste problem in Elbasan is not limited to urban waste. For decades, the city has also been dealing with the consequences of pollution inherited from the heavy industry.
As reported by Ekofin.al, over 1.5 million tons of industrial waste containing heavy metals continue to be deposited in the area of the former Elbasan Metallurgical Combine.
The State Audit Office, in its audit of environmental pollution in the municipalities of Elbasan and Krujë during the 2023–2025 period, has highlighted the lack of a concrete plan for the removal and treatment of these wastes, which contribute to the pollution of the soil, groundwater, and the Shkumbin River.
It remains unclear whether the new €16.77 million project will also address legacy industrial pollution. The general designation of the investment in the government document does not specify the categories of waste that will be treated.
Nearly €60 million for waste management in three zones
With the inclusion of Elbasan, the number of mature projects for integrated waste management infrastructure on the national investment list increases from two to three.
The July list included the project for the Kukës waste area, with an indicative value of €18 million, as well as the one for the Vlorë–Gjirokastër area, valued at €25 million.
With the addition of Elbasan, the combined value of these investments reaches €59.77 million, up from €43 million in July, marking a 39% increase. /ekofin.al