The Municipality of Himarë has launched a public procurement procedure with a budget cap of approximately 150 million lekë excluding VAT for the rehabilitation of the facades and roofs of buildings in the village of Pilur. The investment aims to improve the architectural appearance of this village, preserve the traditional characteristics of the buildings, and protect the existing structures from damage.
According to the tender documents, consulted by ekofin.al, the procedure is an open public works tender and provides for interventions on 75 properties, spread across several areas of the village of Pilur.
The fund for the project’s implementation will be financed by the Himarë Municipality’s budget, spread over two budget years. For 2026, 41.67 million lek without VAT are allocated, while the majority of the funding, approximately 108.33 million lek without VAT, is planned for 2027.
The contract execution period is set at 12 months, while interested economic operators have until December 3, 2026, at 9:00 AM to submit their bids.
The technical project provides for differentiated interventions based on the condition of each building. In some buildings new roofs will be constructed, in others the existing coverings will be rehabilitated, while part of the work will focus on repairing stone masonry, consolidating damaged structures, and improving the facades.
The documentation highlights buildings with partially or fully collapsed roofs, stone masonry exposed to the elements, and structures with reinforced concrete terraces where new coverings are planned.
The interventions aim to preserve the existing footprint of the buildings and the architectural character of the settlement. For this reason, the project specifies the use of materials that are consistent with the traditional typology of Piluri, including natural stone, ceramic tiles, and timber structures.
The new roofs will be constructed primarily with wooden framing and terracotta-toned tiles, with a planned 22% pitch. Meanwhile, the facades will be treated by preserving the natural stone or using light-toned plaster, in accordance with the characteristics of the existing buildings.
The project also includes repairing cracks in the masonry, reinforcing structural elements, fixing gutters and rainwater drainage systems, as well as replacing doors and windows in the buildings where these interventions are explicitly planned.
The architectural report emphasizes that the interventions are not intended to change the overall configuration of the buildings, but to rehabilitate the damaged parts and preserve the existing elements that are valuable to the identity of the settlement.
Piluri is one of the villages in the territory of Himara, located on a hilly landscape above the Ionian coast, with characteristic stone buildings and a traditional settlement structure. /ekofin.al