The modernization of public transport in Tirana continues to fall short of the planned deadlines. The electronic ticketing system, which was supposed to be completed in 2022, had not yet begun to be implemented until the audit by the Supreme State Audit, while only 11% of the main urban roads have dedicated lanes for buses.
According to the KLSH report on road traffic in the Municipality of Tirana, the lack of electronic ticketing has hindered the modernization of payments and more efficient management of urban transport. At the same time, the number of distributed subscriptions has remained unchanged for years, without adjusting to population growth and the real demand of citizens. This shortcoming has caused difficulties in securing passes for regular users.
Road infrastructure also remains problematic. The lanes dedicated to buses cover only 11% of the length of main roads, forcing urban buses to operate in general traffic. The SSA assesses that this situation affects public transport delays and reduces service reliability.
Meanwhile, delays have also been observed in the electric bus rapid transit project, BRT, estimated at around 110 million euros, planned for three main corridors of the capital.
According to the audit, failure to implement activities within deadlines has resulted in financial costs for the Municipality, which paid 47,569.44 euros in 2025 and 62,500 euros in 2026 as a commitment fee for the undisbursed portion of the loan.

In total, these payments amount to 110,069.44 euros. The annual fee is 0.25% of the undisbursed amount and, according to the Supreme State Audit, the costs could have been avoided if the project had progressed according to the specified deadlines.
The municipality has justified the delays with a lack of capacity and expertise, but the Supreme State Audit (KLSH) calls for accelerating investments, implementing electronic ticketing, and expanding dedicated lanes as necessary measures to improve the speed and quality of public transport in the capital. /ekofin.al