Tirana International Airport will carry out an important phase of runway and supporting infrastructure works during November, as part of Kastrati Group’s ongoing investment program, focusing on increasing safety, operational efficiency, and airport infrastructure standards.
The works will take place from November 9 to 26, with planned airport closures during night hours on specific dates within this period. The schedule has been set to minimize the impact on operations, while simultaneously ensuring the necessary time to carry out technical interventions safely and in accordance with relevant standards.
These interventions are part of the preparations for the 2027 season and aim to respond to the continuous increase in air traffic, passenger volume, and increasing market demand. The investments aim to strengthen the capacities of Tirana International Airport and to provide a more modern, sustainable infrastructure prepared for future operational needs. The investments also support the preparation of airport infrastructure for important international events that Albania is expected to host, including the NATO Summit.
The project will include the complete rehabilitation of a significant part of the runway layer, installation of a new airport lighting system with LED technology, improvement of connecting roads (taxiways), as well as other interventions at the terminal.
Due to planned closures during the period from November 9 to 26, some flights may experience changes in departure or arrival times. Passengers who have reservations during this period are advised to be especially attentive to any announcements from their airline and to regularly check the messages and emails used during booking.
In case of a change in a flight’s schedule, the respective airline will inform passengers through the contact details provided in the booking. For this reason, passengers are advised to verify the latest information about their flight before departing for the airport.
Tirana International Airport continues close coordination with airlines and operational partners to minimize the impact of the works and to ensure a safe, coordinated, and efficient process throughout the entire intervention period.