A citizen who chooses the train to go to Rinas Airport in the future will not be able to reach their destination. The railway being built to connect Tirana and Durrës with the airport will stop the passenger a few hundred meters away from the terminal.
A change in the original project has moved the final station outside the airport premises, creating a new problem for passengers: how will they cover the distance to the terminal?
Exclusive documents obtained by Top Channel show that this problem is not an unforeseen consequence of the project. On the contrary, a decision by Albanian Railways supported by the Ministry of Infrastructure led to a change in the station’s location.
In this document dated October 21, 2021, titled “APPROVAL OF THE INFRASTRUCTURE CONSTRUCTION PERMIT: RECONSTRUCTION OF THE DURRËS-TIRANA RAILWAY LINE AND CONSTRUCTION OF THE NEW RAILWAY LINE TO THE RINAS INTERNATIONAL AIRPORT,” THE INITIAL PROJECT APPROVED BY THE NATIONAL TERRITORIAL COUNCIL FORESAW THAT THE STATION WOULD BE BUILT ONLY 60 METERS AWAY FROM THE TERMINAL. But two years later, the Albanian Railways, under the leadership of Ergys Verdho, presented two new alternatives. Within the territory of the Air Force and opposite them.
At that time, the Ministry of Infrastructure, led by Belinda Balluku, through a response from Deputy Minister Hantin Bonati, supported the second alternative by relocating the station outside the airport territory facing the Air Force, shifting the distance from the terminal to about 500 meters.
Ministry of Infrastructure and Energy: “From the perspective of the safety of movement of vehicles and vehicles in the airport and road area, based on the competencies for which the Ministry of Infrastructure and Energy is responsible, and without bypassing or overlapping the competencies foreseen in the sub-loan agreement and the project agreement, our opinion is that your assessment of the second option appears to be the most optimal.”
According to the new project, the station will be completed at a mileage of 5+128, whereas in the existing project the end of the line was planned at kilometer 5+800. Thus, the railway segment is shortened by about 672 meters.
Albanian Railways considers this reduction a good decision that would save the institution’s budget funds to be used for other needs, the documents say. Meanwhile, the only concern is the distance for passengers in wheelchairs and disabled persons.
Albanian Railways: “The length of pedestrian movement is acceptable; in the case of passengers in wheelchairs, disabled persons, and luggage, it will definitely require an express service called “shuttle-navetta” which will be under passenger rail operation service, a relatively solvable issue considering that the same principle exists in many other European airports.”
What stands out in the documentation is that state institutions have taken care to define the financial conditions and implementation deadlines, but not a final and detailed solution for passenger transport to the terminal.
Sources for Top Channel report that this change has also raised concerns from the European Bank for Reconstruction and Development, but when officially asked, they told us they are aware of the problem.
European Bank for Reconstruction and Development: “EBRD is aware of the relocation of the railway station that will serve Tirana International Airport. EBRD is cooperating with Albanian Railways and other parties to assess the impacts of this change and to identify an appropriate solution that guarantees a safe and efficient connection for passengers between the railway station and the airport terminal.”
EBRD reiterates that it is a co-financier, while the responsibility for implementation and decision-making regarding the project lies with the Albanian institutions.
The Tirana-Rinas-Durrës railway, an investment of around 130 million euros by the Albanian government together with the European Bank for Reconstruction and Development, is expected to open a new era of Albanian railways with a travel time of 22 minutes and a speed of 120 km/h.
A project that started to bring the airport closer to rail transport now must also resolve the distance created by the project change itself. But while projects continue on paper and on the ground, the question that Albanian Railways and the Ministry of Infrastructure still need to answer citizens is who will transport passengers to the terminal and at what cost?/Top Channel