The Municipality of Tirana has completed the tender procedure for the project “Reconstruction of the secondary road Tirana-Durrës for the segment from Hygea hospital to Megatek,” announcing the winning consortium of economic operators “Vëllezërit Hysa” sh.p.k. & “Ergi” sh.p.k.
The value of the selected offer is 4.3 million euros (386,510,064.08 lek). This offer was qualified as the lowest-priced among operators who met the technical criteria, while the deadline set for completing the works is 5 calendar months from the signing of the contract.
The mentioned road axis is about 6.8 kilometers long and runs parallel to the Tirana-Durrës highway, from the roundabout at the “Hygea” hospital to the Rinas overpass.

This segment serves as an access road for the industrial zone and surrounding villages (such as Laknas and Domje), as well as to ease traffic flow on the highway. The current condition of the route is characterized by significant damage to asphalt layers, sidewalks worn out by 70%, and inefficiency of the public lighting network and rainwater drainage.
According to the implementation project, the technical intervention will include excavation of the existing structure and paving of a new road package with four layers: asphalt, binder, bituminous conglomerate, and stabilizer.
The new carriageway will be 6.5 meters wide, divided into two lanes of 3.25 meters each in each direction of travel. At the same time, sidewalks will be rebuilt with self-compacting concrete slabs and access ramps, and decorative trees will be planted every 6 meters.
Regarding the underground infrastructure, rainwater will be managed through new manholes that will discharge into the concrete channel that ARRSH is constructing parallel to the highway.
Additionally, a new LED lighting network with poles every 28 meters will be installed, new underground lines for telephony and fiber optics, as well as a dedicated MNZ network with underground hydrants every 100 meters. /Kapitali.al