The latest government decision regarding the new rules for the evaluation, approval, and awarding of concession and public-private partnership (PPP) contracts has been published in the Official Gazette, strengthening control over costs, fiscal risks, and obligations that these projects may create for the state budget.
One of the main elements is the role of the Ministry of Finance, which must assess the impact of projects on budget expenditures, the deficit, the sustainability of public debt, and any possible financial obligations that may arise during the implementation of contracts.
The new rules are based on Law no. 88/2025, “On Concessions and Public-Private Partnerships,” and aim for decision-making for these projects to be based on economic, financial, and risk analyses.
Feasibility study, a condition for project evaluation
According to the decision, before a project proceeds to the concession or PPP awarding procedure, the contracting authority must assess the need for investment and the most appropriate way to carry it out.
Projects can be identified through national, regional, or sectoral strategies, analysis of infrastructure and public service needs, as well as government policy priorities.
A special commission is established to review them, which prepares a preliminary report on the necessity and suitability of the project. The feasibility study must analyze not only the expected costs and benefits but also economic sustainability, social and environmental impact, as well as the risks that may accompany implementation. An important requirement is to compare the concession or PPP model with the alternative of traditional public procurement. The project must justify that implementation through partnership with the private sector is more beneficial than the traditional alternative.
Stronger control over risks to the budget
The documentation submitted for approval to the Ministry of Finance must include the draft contract, the cash flow statement, and a detailed risk analysis. This analysis must identify the probability of the risk materializing, the period when it may arise, the financial impact, and the distribution of possible costs over the years.
Also, the party responsible for each risk, the measures to limit it, and the possible sources of funding in case it materializes must be determined. These requirements aim to highlight not only the direct payments that the state may undertake but also contingent liabilities, that is, liabilities that may arise in the future depending on the development of the project.
In this way, the financial evaluation is not limited to the initial cost of the investment but also extends to the long-term impact that the contract may have on public finances.
Contract changes and transfers to other operators require prior approval
One of the most important provisions of the decision concerns the amendment and transfer of concession and PPP contracts.
According to Article 40, any contract change or transfer undertaken in accordance with the law must be submitted to the Ministry of Finance for prior approval. The contracting authority must provide a written justification for the change and provide supporting documentation.
In addition, a qualitative and quantitative report on the risks and financial impact that the change or transfer may have throughout the duration of the contract is required.
This means that contractual changes must be evaluated not only from the perspective of the relationship between the public institution and the private operator but also for their effects on the budget, deficit, and public debt.
Contracts will undergo final evaluation before signing
After concluding negotiations with the winning operator, the contracting authority must send the contract, annexes, and an explanatory report for final evaluation to the Ministry of Finance. The report must highlight possible changes from the initially submitted draft contract and their compliance with the approvals granted.
For projects of central institutions that require financial support and involve fiscal risks, the relevant approval by the Council of Ministers is made before signing the contract and after the final evaluation by the Ministry of Finance.
Studies must be reassessed if the project is delayed by more than two years
The decision also establishes a mechanism to avoid the use of feasibility studies that may no longer reflect the economic and financial conditions of the project. If within two years from the Ministry of Finance’s approval the winning operator is not announced, the contracting authority must resubmit the revised feasibility study for approval before announcing the procedure.
Re-approval is also required when the study undergoes changes after its initial submission to the Ministry of Finance.
Rules for competition and selection of operators
The decision also establishes procedures for competition and the selection of private operators.
In negotiated procedures, contracting authorities must ensure equal treatment of bidders and not provide information that could favor certain participants.
The subject of the concession, the minimum requirements, and the criteria for awarding the contract cannot be changed through negotiations.
In cases where suitable offers are not submitted or the procedure does not ensure the required competition, its cancellation and an analysis of the reasons before initiating a new procedure are foreseen.
For public-private partnership contracts, public procurement rules apply, insofar as they do not conflict with the special law on concessions and PPPs. /ekofin.al