The Energy Regulatory Entity (ERE) has approved the 5-year Development Plan for the Electricity Distribution Network for the period 2023–2027, which foresees investments worth over 53.5 billion lek, or about 587 million euros, including financing from the Distribution System Operator (OSSH) and foreign capital.
Decision no. 292, dated October 20, 2026, was published today in the Official Gazette and includes a detailed list of investments, from the construction and reconstruction of electrical substations to the strengthening of distribution lines, network modernization, metering systems, and monitoring technologies.
According to the approved document, the investments planned with OSSH funds reach 47.54 billion lek, while foreign capital financing is estimated at around 6 billion lek.
The plan aims to improve the security and quality of electricity supply, reduce network losses, and increase capacities to meet consumer demand, especially in areas with rapid urban and tourist development.
The year 2027, the highest investments of the period
From the annual distribution of investments financed by OSSH, it appears that 2027 is expected to have the largest volume of financing, around 12.45 billion lek.
For 2026, the plan includes 8.87 billion lek in investments with the operator’s funds, while for 2024 and 2025, respectively, 11.83 billion and 11.62 billion lek are forecasted.
These figures represent the values of the updated plan and not necessarily the investments made in each year.
A significant portion of the funding has been directed towards electrical substations, for which 11.81 billion lek are planned over the five-year period.
Another important item is the construction and reconstruction of the medium and low voltage network, with about 15.74 billion lek, while about 3.93 billion lek are allocated for the construction of the medium voltage network.
New substations and network strengthening in several cities
The plan includes a large number of interventions in the country’s electrical infrastructure, aiming to eliminate weak points in the network and improve supply in areas with high demand.
In Tirana, among the planned projects is the strengthening of the Zogu i Zi substation, with a total value of 650 million lek, as well as interventions at the Palace of Congresses and Lanabregas substations.
In the Durrës area, the strengthening of the Golem substation is included, with a value of 175 million lek, while in Shkodër, investments are planned for the reconstruction of the Shkodra 1 substation and the improvement of distribution infrastructure.
In the south of the country, the investments include the construction of a new substation in Akërni and the development of the power line to Vlora Airport, with a planned value of 427 million lek.
Additionally, interventions are planned at the substations of Delvina, Xara, Piqeras, and other areas where tourism development and the expansion of economic activity require greater supply capacities.
In Fier, the construction of the new Fier 2 substation is included, valued at 600 million lek, while in Kuçovë, the reconstruction and strengthening of the existing substation is planned, valued at 650 million lek.
Investments also in network measurement and monitoring
Part of the plan is dedicated to the technological modernization of the distribution system.
For investments in metering, about 1.87 billion lek are planned, while for another category of investments in the metering system, 1.04 billion lek are planned.
Approximately 552 million lek have been allocated for network monitoring technologies.
These investments aim to improve network management, identify technical problems, and control losses, creating conditions for a more efficient energy distribution system.
About 6 billion lek in foreign capital financing
In addition to investments with its own funds, OSSH has also included projects financed with foreign capital in the plan, with a total value of around 6.01 billion lek.
Of this amount, about 3.25 billion lek are related to financing from the German bank KfW, which includes the expansion of the SCADA system, the reconstruction of substations in the Tirana–Durrës regions, and the construction of the Kamza–Valias substation.
The plan also includes financing of about 1.72 billion lek for the Center substation, connected to the European Bank for Reconstruction and Development, as well as about 1.04 billion lek within the framework of Italian cooperation for Himara.
ERE establishes inspections every six months to ensure the implementation of investments
An important element of the decision is the obligation for periodic monitoring of the plan’s implementation.
ERE has decided that OSSH will report every six months on the progress of investments planned for the years 2026–2027.
Reporting must include planned and realized values, the physical and financial progress of projects, as well as explanations for deviations from deadlines or approved costs.
Additionally, the operator must report the impact of investments on network performance indicators, including the duration and frequency of power outages, unsupplied energy, and the level of losses.
Any significant change in the object, value, technical parameters, or investment deadlines must be notified to ERE and, when required by the regulatory framework, subject to new approval. /ekofin.al