Companies that win public tenders may no longer be limited to subcontracting up to a maximum of 50% of the contract value. The government proposes removing this limit in the draft law amending Law no. 162/2020, “On Public Procurement” (as amended), while also introducing new rules for modifying contracts without tender and controlling the companies involved in their implementation.
According to the current law, Article 126 stipulates that the portion of the contract that can be transferred to subcontractors must not exceed 50% of the total value. The draft law, in Article 56, proposes the repeal of this provision without setting an additional limit in its place.
If approved, the change will allow winning operators to subcontract a larger portion of the contract. However, removing the threshold does not imply removing the responsibilities of the main contractor or obligations to verify subcontractors.
On the contrary, the draft law adds several control mechanisms. The winning company must notify the contracting institution of any changes during the implementation of the contract and the inclusion of new subcontractors.
Authorities will also be able to request information about the subcontractors of these companies, extending control to other links in the chain. If a subcontractor is found to meet the legal disqualification criteria, the institution must request their replacement.
Contract changes, up to 15% without a new tender
Likewise, the legal provisions foresee another possibility for modifying public contracts during their implementation.
More specifically, contract modification will be allowed without conducting a new procurement procedure, when the modification value is below the high monetary threshold and does not exceed 10% of the initial value for goods and services or 15% for public works.
For example, for a public works contract valued at 100 million lek, the percentage limit of this mechanism would be 15 million lek, but only if the high monetary limit and other legal conditions are also respected.
This provision does not automatically replace the current rules. The current law allows the modification of contracts without a new tender in certain circumstances and sets a limit of 20% of the initial value for certain categories of changes. The draft law revises the scope of application of this limit, while adding a special mechanism with thresholds of 10% and 15%.
In any case, modifications must not change the general nature of the contract. To avoid circumvention of the rules, successive changes will be assessed based on their cumulative value.
When can the winning company be replaced?
The draft law also clarifies the cases when another operator can replace the company that initially won the tender.
This can happen when the replacement is foreseen in the original contract or when the new operator is the legal successor of the winning company, due to a change in ownership, merger, division, or bankruptcy.
The company undertaking the contract must meet the initial tender requirements, and the replacement must not bring other substantial changes or be used to circumvent procurement rules.
The draft law also adds the possibility of terminating the contract in cases where it turns out that the economic operator, at the time of awarding it, was in conditions requiring disqualification from the tender. /ekofin.al